THE COSTS:
DEMOLISH or RESTORE THE NATATORIUM??
More About the Waikiki War Memorial Natatorium
A Side-by-Side Comparison of Estimated Costs
Historic Hawaii Foundation

HISTORIC HAWAI‘I FOUNDATION   
Spencer Beach Park
Old Wailuku Inn, Maui
Palm Circle at Ft Shater
Kaniakapupu
Molokai
Maui
During the course of the Mayor's Task Force 2009 meetings, the Mayor's consultants and staff presented various quotes of costs for alternatives uses for the War Memorial's site. In order to present a fair comparison of all of the costs, Historic Hawaii compiled them into a comprehensive table.   Historic Hawaii Foundation submitted these figures to Collins Lam, chair of the Mayor's Natatorium Task Force in July and then reviewed them with the Mayor's staff prior to the Historic Hawaii Foundation presentation at the August 27th Task Force Meeting.  The sources for these numbers are reflected in the right-hand column. 
Natatorium Cost Comparisons

Natatorium Cost Comparisons

Main Component Cost Status Quo/ Collapse Containment Restore to 1927 Natural Shoreline Stabilize Structure (1999 modified plan) Rehab structure + Redesign new pool Demo + Build Beach (Scenario 3a) Rehab structure + 1999 Plans + DOH pool Notes on Sources
Demo pool, piles & debris n/a $1,440,000 Included $1,440,000 $1,440,000 Included Included in the "complete the restoration" line below
Demo bleachers, parking lot, volleyball court n/a $400,000 n/a n/a $400,000 n/a C&C of Honolulu
Construct Diamond Head, ‘Ewa Groins n/a n/a n/a n/a $838,000 n/a ACE
Quarry Run n/a n/a Included $234,000 $234,000 Included ACE
Sand fill, new beach n/a n/a n/a n/a $2,715,000 n/a ACE
Sand fill, Kaimana Beach n/a n/a n/a $300,000 $300,000 $300,000 Wil Chee presentation
Repair Kapi‘olani Park contruction staging area ? $700,000 n/a n/a $700,000 n/a Wil Chee presentation
Rebuild the arch n/a n/a n/a n/a $1,400,000 n/a Wil Chee presentation
Dredge silt from the pool area n/a $1,800,000 Included $1,800,000 $1,800,000 Included Silt to be encapsulated with restoration, for others: source wil chee
Remove part of wall $300,000 n/a n/a n/a n/a n/a Wil Chee presentation
Apply bleacher coating (Alternative A) $270,637 n/a $270,637 n/a n/a n/a Wil Chee - Emergency Preparedness Report
Warning signs $5,000 n/a n/a n/a n/a n/a Wil Chee presentation
Fence Pool $30,000 n/a n/a n/a n/a n/a Wil Chee presentation
Geonet $2,000,000 n/a n/a n/a n/a n/a Wil Chee presentation
Build restrooms n/a $650,000 n/a n/a $650,000 n/a Task Force Meeting 1 minutes
Repair finishes (interior and exterior) n/a n/a   $1,500,000 n/a $1,500,000 Wil Chee presentation
Complete the 1999 restoration/stabilization plan as revised 2004 n/a n/a $5,800,000 n/a n/a $5,800,000 Note= $5.8 million is 2004, inflation adjustment below
Construct cleanable sides and bottom (DOH rules) n/a n/a n/a Included n/a $20,000,000 C&C of Honolulu; range $15M-$20M
Pumps and Circulation (DOH rules) n/a n/a n/a $1,000,000 n/a $1,000,000 C&C of Honolulu
Floating Dock n/a n/a n/a n/a n/a $200,000 C&C of Honolulu
Pool equipment for accessibility n/a n/a $0 n/a n/a $60,000 C&C of Honolulu
Seawall Diving barrier n/a n/a $200,000 $200,000 n/a $200,000 C&C of Honolulu
Build a redesigned Pool & Deck (DOH rules)       $3,750,000     $250 per square foot, 15,000 sq feet x 250 = $3,750,000 Source: Aquatic Design Group
Mobilization minimal $1,200,000 $1,200,000 $1,200,000 $1,200,000 $1,200,000 Task Force meeting #2
EIS $ 250,000 $ 250,000 $ 250,000 $ 250,000 $ 250,000 250,000 C&C of Honolulu
Permitting $200,000 $200,000 $200,000 $200,000 $200,000 $200,000 C&C of Honolulu
Mitigation (for demo of historic site, environ. damage) Unknown Unknown $0 Unknown Unknown Unknown Only "Stabalize" completed historic, environ. review -- no mitigation req.
Subtotal $ 3,055,637 $ 6,640,000 $ 7,920,637 $ 11,874,000 $ 12,127,000 $ 30,710,000 Construction costs
Phasing premium           $ 6,142,000 Phased implementation w/ stabilize=20%
Engineering and architectural design $305,564 $996,000 $1,188,096 $1,781,100 $1,819,050 $4,606,500 General Guidelines
Contingency $ 672,240 $ 1,527,200 $ 1,821,747 $ 2,731,020 $ 2,789,210 $ 7,063,300 20%
TOTAL $ 4,033,441 $ 9,163,200 $ 10,930,479 $ 16,386,120 $ 16,735,260 $ 48,521,800  
Adjusted for inflation $ 12,532,479 $ 50,123,800
Operations & Maintenance Low Low Medium High Medium High
Optional Add ons
Handicap accessible sidewalk and ramp n/a n/a   $1,300,000 n/a $1,300,000  
Landscape and lighting improvements n/a n/a   $140,000 n/a $140,000  
Volleyball Court Improvements n/a n/a   $50,000 n/a $50,000  
Repave parking lot n/a n/a   $100,000 n/a $100,000  
The Least You Need to Know
  • Demolish the memorial & return the area to natural rocky shoreline = $9,163,200
  • Restore the memorial with a re-engineered pool = $16,386,120*
  • Demolish the memorial and construct a sandy beach = $16,735,260

* Historic Hawaii Foundation's recommended scenarios